Water Treatment Plant Expansion and Wellfield Improvements
Summary
The city is bringing in a new completion contractor, Lawrence Lee Construction Services, after the previous contractor defaulted. A $4.06 million payment from the insurance surety covers the cost difference to finish the project.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 9, 2026.
Impact analysis
The surety will pay the city $4,067,612.52 to cover the cost difference, resulting in zero out-of-pocket expenses for the city.
Melbourne water utility customers and residents who rely on plant capacity expansions.
No groups negatively affected
Mentions & discussions (3)
City Council - Sep 9, 2026
The city is bringing in a new completion contractor, Lawrence Lee Construction Services, after the previous contractor defaulted. A $4.06 million payment from the insurance surety covers the cost difference to finish the project.
City Council - Jul 14, 2026
The city is advancing major utility projects, including designing Production Well No. 8 and extending reclaimed water and wastewater force mains, to expand the Reverse Osmosis Water Treatment Plant's capacity from 5 to 10 million gallons per day.
Temporary Change in Water Treatment Begins Monday, Jan. 5
Temporary Change in Water Treatment Begins Monday, Jan. 5 City of Melbourne, Florida
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Melbourne
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.