Temporary data center moratorium
Summary
The county is under a moratorium while it drafts data-center standards covering noise, lighting, setbacks, and emissions — and this application was filed before those rules existed. Several commissioners stressed any approval should require compliance with future LDC standards.
At a glance
- Total mentions
- 7
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 15, 2026.
Impact analysis
Unknown — the county is still gathering input before writing the data center rules.
Residents gain protective standards before any data center is approved.
Data center developers and industrial landowners face delayed permitting, and the county risks a Bert Harris takings claim for a prolonged ban.
Mentions & discussions (7)
Planning and Development Commission - Oct 15, 2026
Staff collected dozens of public comments on the first data center ordinance draft and will post a revised version in November, aiming for public hearings around the first of the year before the moratorium ends.
Planning and Development Commission - Jun 18, 2026
The county is under a moratorium while it drafts data-center standards covering noise, lighting, setbacks, and emissions — and this application was filed before those rules existed. Several commissioners stressed any approval should require compliance with future LDC standards.
Board of County Commissioners Regular Meeting - Jun 11, 2026
A one-year moratorium gives staff time to write data center land-use rules; an application to add data center language at Holder Industrial Park goes to the PDC in June and the board in July.
Planning and Development Commission - Jun 4, 2026
Staff pulled a citizen-drafted data center ordinance from the July agenda because the County Commission has a moratorium in place. A heavily attended June 18 meeting on the Holder Industrial Center is next, with interveners possible.
Board of County Commissioners Regular Meeting - May 26, 2026
The county put a one-year pause on data center permits, development orders and rezonings while it crafts a strict permanent ordinance. Residents packed the chamber opposing the Holder Industrial Park data center over water, power, noise and health concerns.
Board of County Commissioners Regular Meeting - May 12, 2026
Residents packed the room opposing a proposed AI data center near Holder, citing water demand of up to 10 million gallons a day, noise, power demands, and forever chemicals. The board unanimously directed staff to draft a moratorium ordinance — up to 12 months — while it finishes data center regulations for the Land Development Code.
Planning and Development Commission - May 7, 2026
A telecom veteran urged commissioners to get educated before the May 21 data center hearing, offering free briefings, and noted a BOCC moratorium vote was imminent this week.
Related development
Holder Industrial Park / proposed data center
Residents fear aquifer depletion, noise, traffic, and harm to wildlife and the Nature Coast economy if the data center is approved.
Holder Industrial Park data center language application
Could open the county's largest industrial park to data center uses once standards are written.
CPA-AA-2025-00013 — Holder Industrial Park Sub-Area Plan Expansion / Data Center Use Area
Nearly 1,300 acres of heavy industrial next to rural residential neighborhoods, with data centers allowed by right — approved uses would go straight to permitting with no further public hearings.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Citrus County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.