Holder Industrial Park / proposed data center
Description
The proposed heavy industrial rezone and hyperscale data center at Holder dominated public comment, though the rezoning itself was not up for a vote today — hearings are set before the PDC and then the BOCC. Speakers raised aquifer depletion, saltwater intrusion, noise, generator emissions near three schools, and questionable job claims.
Impact summary
Residents fear aquifer depletion, noise, traffic, and harm to wildlife and the Nature Coast economy if the data center is approved.
Applicant
- Name
- Deltona Corporation
At a glance
- Hearings
- 2
- Public comments
- 2
- Total mentions
- 2
Recorded in the meeting · County Commission
Last discussed Jun 22, 2026.
Meeting timeline (2)
Board of County Commissioners Regular Meeting - Jun 22, 2026
Deltona's request to delay its heavy-industrial rezoning (widely understood as a data center) to November was unanimously denied; the final hearing remains July 14 after the PDC recommended denial 7-0.
Board of County Commissioners Regular Meeting - May 26, 2026
The proposed heavy industrial rezone and hyperscale data center at Holder dominated public comment, though the rezoning itself was not up for a vote today — hearings are set before the PDC and then the BOCC. Speakers raised aquifer depletion, saltwater intrusion, noise, generator emissions near three schools, and questionable job claims.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Citrus County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.