Alice Hall Community Center replacement
Main Street Zephyrhills reported progress on the historic theater: demolition plans approved, $2.5 million in state money secured, and about $729,000 spent. Council pressed for clarity on project management and who's responsible as fundraising continues.
New GIS data hub for public access
The city launched a new mapping website where residents can check if they're in city limits and businesses can look up zoning without calling city hall — a transparency and business-friendliness upgrade.
City-branded bike racks at transit stops
Nine new Zephyrhills-branded bike racks are ready for installation at bus stops and the future transfer station, with council expressing interest in expanding them downtown and at parks.
Fleet lease-versus-purchase study
Council asked staff to analyze whether leasing big-ticket vehicles like garbage trucks makes more sense than buying, especially with Amendment Three budget pressure looming.
Amendment Three and House Bill 1451 fiscal impact
The November ballot measure could cost the city about $2.3 million in property tax revenue in 2028 and $3.2-3.5 million total. Council is urging caution on spending and debt.
City Yard Complex contingency spending
The council locked in the maximum price for the long-planned city yard rebuild at just under $26 million — about $1.9 million under early estimates. Construction runs about 18 months on an occupied campus, wrapping up in September 2027.
Utility Service Annexation Tracking
The city serves utility customers outside city limits, and state law can force annexation when a served property becomes contiguous with the city. Those parcels aren't mapped, so council directed staff to add them to the GIS system.
Downtown Plaza Tree Removal
Councilman Spina wants more data before deciding whether the Clock Plaza redevelopment preserves the existing live oaks — an arborist evaluation and cost estimate will come back September 28.
Daughtery Road Sidewalk Extension Cost
Kimley Horn wanted $62,000 to design just 750 feet of sidewalk on Daughtery Road — far more per foot than recent city sidewalk projects. Council pulled the item and ordered a competing bid, citing over-reliance on long-term engineering firms.
Commandoughs Veterans Day Wet Zone
March 28, downtown 5th Avenue becomes a wet zone — buy a drink at a downtown bar and carry it through the festival.
Greenway Loop Trail Concept Plan
A conceptual plan would link Sam Pasco Park, Zephyr Park, 8th Street businesses, Hercules Park, and eventually the U.S. 301 trail toward Dade City, with safety features like bollards and wayfinding signage.
City Attorney Contract Renewal and Legal Costs
Legal rates are going up from $250 to $350 an hour under a three-year renewal, and last year the city spent about $277,000 against a $275,000 budget. Council will now get monthly billing statements and review costs at mid-year.
Existing Trail Safety Retrofits
Dr. Spina raised recent pedestrian fatalities, including one on Dairy Road, and asked about crosswalks, lighting and coordination with county and state agencies.