Electric undergrounding progress and outage communication

Summary

The undergrounding program is 84.74% complete citywide with about 19 miles remaining; the board debated whether the ~$11 million annual undergrounding spend frees up cash when done — staff said future infrastructure needs mean it likely won't.

At a glance

Total mentions
4
Last 30 days
0

Last discussed Aug 25, 2026.

Impact analysis

💰Financial impact

About $11 million a year going to undergrounding now; future spending will depend on commission decisions on substation, meter, and street-lighting projects.

✅Who benefits

All electric customers through improved reliability and storm resilience, plus better tree canopy in undergrounded areas.

⚠️Who could be affected

Northwest residents near Park Maitland School who experienced a prolonged outage with poor communication.

Mentions & discussions (4)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Winter Park

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.