Electric undergrounding program status
Summary
Overhead-to-underground conversion is about 84% complete on mainlines, with roughly $4 million spent this fiscal year; commissioners asked when Minnesota and Denning streets get their turn.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 13, 2026.
Impact analysis
About $4 million spent this year against a $9.9 million budget; contracts authorize up to $10.7 million more for conversion work.
Residents in converted neighborhoods get more reliable power and better streetscapes.