Logistics Parkway Extension Construction Change Order
Summary
The commission reviewed a $119,827 change order for the Logistics Parkway extension project to cover unexpected drainage issues, roadway elevations, and gopher tortoise relocations.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 22, 2026.
Impact analysis
Increases project cost by $119,827 to a total of $5,434,361, funded through the transportation fund.
Nearby industrial facilities and motorists utilizing the new roadway corridor.