Grand Isles Settlement for 120th Avenue Roundabout
Summary
Wellington is moving forward with a $4.29 million contract for intersection roundabout improvements at 120th Avenue South and Lake Worth Road. However, staff and council must resolve an unexpected property access dispute with the Grand Isles POA and their attorneys regarding canal drainage tracts before construction can proceed smoothly.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Mar 24, 2026.
Impact analysis
Project costs total approximately $4.29 million for construction and $200,000 for engineering services, funded via gas tax capital funds and contributions.
Motorists and area residents traveling through the 120th Avenue and Lake Worth Road corridor will experience improved traffic safety and flow.
Residents and drivers may experience traffic disruptions during the 9-month construction period spanning into the school year.
Mentions & discussions (3)
Village Council — March 24, 2026
The council authorized agreements and a legal settlement to acquire necessary right-of-way for building a roundabout at Lake Worth Road and 120th Avenue.
Village Council Workshop — March 23, 2026
The village reached a settlement agreement with Grand Isles to acquire land for a roundabout near Panther Run Elementary, avoiding eminent domain battles and settling legal fees.
Village Council Workshop — March 9, 2026
Wellington is moving forward with a $4.29 million contract for intersection roundabout improvements at 120th Avenue South and Lake Worth Road. However, staff and council must resolve an unexpected property access dispute with the Grand Isles POA and their attorneys regarding canal drainage tracts before construction can proceed smoothly.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wellington
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.