Summary
The village is moving forward with a $5.69 million project to upgrade six stormwater pump stations and replace a generator, alongside a grant-funded resilience adaptation plan to address flood vulnerabilities.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 6, 2026.
Impact analysis
Total project costs exceed $5.8 million across pump station upgrades and adaptation planning, largely offset by state grants.
Wellington residents and property owners benefit from enhanced flood protection and improved stormwater management.
Mentions & discussions (2)
Village Council Workshop — August 6, 2026
A multi-year, $43.8 million stormwater program is underway to refurbish critical pump stations like numbers 3, 4, 6, 7, and 9 to like-new condition. These stations protect homes from flooding during heavy storms by moving water out of the basin quickly.
Village Council Workshop — July 27, 2026
The village is moving forward with a $5.69 million project to upgrade six stormwater pump stations and replace a generator, alongside a grant-funded resilience adaptation plan to address flood vulnerabilities.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wellington
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.