Rolling Terrace Retention Pond Drainage
Summary
FDOT is paying the full $869,138.20 to restore the 7.61-acre borrow pit and then hand it to the city, adding it to the stormwater system. Council members quizzed staff on how it affects flooding near the neighboring apartment complex.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 7, 2026.
Impact analysis
No local cost — FDOT funds the entire $869,138.20 project; the city takes on future maintenance.
Residents in the northwest part of the city get improved stormwater handling at no cost to taxpayers.
The adjacent apartment complex parking lot remains part of the designed flood compensation area during severe storms.
Mentions & discussions (2)
City Council - Jul 7, 2026
A resident returned to thank the city for acting on the flooding subdivision's retention pond after Hurricane Milton — drainage improvements are in place and residents are hopeful.
City Council - Apr 7, 2026
FDOT is paying the full $869,138.20 to restore the 7.61-acre borrow pit and then hand it to the city, adding it to the stormwater system. Council members quizzed staff on how it affects flooding near the neighboring apartment complex.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Temple Terrace
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.