Wastewater treatment facility electrical upgrades rebid
Summary
Two consent contracts would keep critical wastewater treatment equipment maintained: OVIVO OEM parts for the plant built in 1986 and Flygt submersible pumps. These keep the plant compliant with state disinfection requirements.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jul 28, 2026.
Impact analysis
Up to about $80,000 a year for the OVIVO parts contract, plus the Flygt award amount.
Residents who rely on the city's wastewater service and clean water compliance.
Mentions & discussions (2)
Board of Commissioners - Jul 28, 2026
All bids for electrical upgrades at the wastewater plant were set to be rejected, meaning the project will have to be rebid. Treatment capacity and reliability aren't affected right away.
Board of Commissioners - Jun 23, 2026
Two consent contracts would keep critical wastewater treatment equipment maintained: OVIVO OEM parts for the plant built in 1986 and Flygt submersible pumps. These keep the plant compliant with state disinfection requirements.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tarpon Springs
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.