Clerk's office building change order
Summary not yet generated for this topic.
Community sentiment
At a glance
- Public comments
- 3
- Last 30 days
- 0
Last discussed Mar 24, 2026.
Public comments (3)
DMAR's vice president explained the company's COVID-era upheaval, said they've invested about $500,000 of their own money and forfeited $200,000 in profit, and urged approval to finish the project.
Board of Commissioners - Mar 24, 2026 · 1:30:06 →A former Clearwater councilwoman now with DMAR cited incomplete plans, three hurricanes, and storm mitigation work, and asked the board to approve so the project can reach ribbon-cutting.
Board of Commissioners - Mar 24, 2026 · 1:37:40 →Asked what's gone wrong with city projects — pointing to ponding water on Gross Avenue and the clerk's office costs — and urged the board to find the root cause.
Board of Commissioners - Mar 24, 2026 · 1:41:03 →