Pass-a-Grille Channel dredging and beach nourishment
Summary
A county/Army Corps dredging project will deepen the Pass-a-Grille Channel and place the sand on Pass-a-Grille beach, with temporary construction easements on city right-of-way. Work should finish by May 2027.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 19, 2026.
Impact analysis
The project is funded through the Army Corps dredging mechanism, not city beach-nourishment dollars.
Boaters (better navigation) and Pass-a-Grille beach users (more sand).
Users of parking spaces temporarily closed for equipment staging.