Public comments (2)
NeutralBennett RabinOct 12, 2026
Attorney for the association cited hurricane damage, a bankrupt contractor and Duke Energy delays in asking for leniency on fines.
Special Magistrate - Code Enforcement - Oct 12, 2026 · 0:00 →NeutralBlair NewtonOct 12, 2026
Property manager said Duke Energy needs 60-70 days to replace leased poles and lights can't simply be turned off for safety reasons.