Glades Cut Off Road signalization
Summary not yet generated for this topic.
Community sentiment
Neutral (1)
At a glance
- Public comments
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Public comments (1)
NeutralRobert AustinbergOct 13, 2026
Greenpointe Developers' VP told the board the DRI never required the Glades Cut Off signal — the developer voluntarily installed the ~$600,000 span-wire signal for safety — and asked all three parties to split the $542,702 FEC tie-in cost. He also offered to install temporary warning signage.
Board of County Commissioners - Oct 13, 2026 · 1:46:01 →