Hillview Drive drainage improvements
The Hillview Drive drainage project got a $1.06 million change order and 210 more days on its construction timeline — work meant to fix flooding in the area.
Moving Seminole — Public Works & Mass Transit
Ridership has doubled since replacing Lynx routes and the county is saving $1.7 million a year. Fares are being tweaked: cheaper SunRail connections, pricier peak trips for non-discounted riders.
Oxford Road sidewalk stormwater project delays
Residents of English Estates told the Board the long-running contractor project is unsafe, behind schedule, and unsupervised. Public Works pushed back, saying three to four crews are on site and the project remains on track for completion by year-end.