Stormwater and Right-of-Way Maintenance
A resident flagged knee-high weeds on Floresta between Port St. Lucie Boulevard and Crosstown; the city manager agreed to have staff look at mowing.
Citywide flooding and emergency response
An unprecedented rain event flooded streets across Port St. Lucie, filled the stormwater basin, and damaged spillways. The city declared an emergency, opened shelters, and is asking residents to stay home while crews work to move water off roadways.
Failed septic system discharging sewage
11,402 septic conversions have been done since 1999, with 12,210 systems left. Council discussed mandatory connection rules (currently illegal at home sale), grant funding that may require forced connections, and the cost burden on fixed-income residents.
Utilities department customer service complaint
A resident described a frustrating three-hour ordeal getting water service restored at her rental property after staff demanded an incorrect form; the city manager pledged to review the case as a lessons-learned.
150-foot cell tower in Tradition
A 150-foot monopole behind the self-storage facility would improve spotty cell service in Tradition but residents within a mile say it would loom over backyards and hurt property values. The board recommended approval; Council makes the final call.
Cigna–HCA Florida health network dispute
No agreement has been reached between Cigna and HCA Florida, which could disrupt health coverage for city employees and their families. The city says it's monitoring the situation; the union wants contingency plans given the financial consequences.
Utility Rate and Fee Increases
Staff proposed a 3.5% water rate increase (about $1.29 more per month on a typical bill), higher connection and septic conversion fees, and no sewer rate increase this year. An ordinance will come to Council for adoption.
Utility Easement Abandonments
Ordinance 26-91 would abandon part of a 20-foot-wide rear utility and drainage easement behind a lot in Section 19, a routine but owner-specific land action.
Utility Rate Increase for Water, Wastewater and Reclaimed Water
Water and sewer customers will pay about $1.29 more per month under a 3.5% rate increase the council approved unanimously. Officials framed it as a slow, incremental approach to keep up with rising energy and operating costs.
Swale and culvert replacement program acceleration
Council raised a resident's complaint that a culvert was replaced though inspection suggested it wasn't needed; staff confirmed work was completed and paid but will investigate the inspection process and respond to the homeowner.
Citywide LED Streetlight Conversion
New energy-efficient, glare-controlled LED lighting is going in on the tennis, pickleball, basketball, volleyball, playground, and parking areas at Winterlakes Park — more evening play, less light spillover.
Affordable culvert and drainage repairs for homeowners
The city will use the county Tax Collector to collect assessments against benefited homes for the voluntary culvert replacement program, recovering the city's costs.
Annual water disinfection flush
From July 6-17 the city temporarily changes its water disinfection process — routine annual maintenance required by regulators.
Glades Wastewater Treatment Facility Expansion
The consent agenda included a contract for a second deep injection well at the Glades Wastewater Treatment Facility and an amendment for inspection services on the Westport facility's nutrient reduction project. Both support the city's sewer capacity and environmental compliance.
Discovery (Rangeline) Water Treatment Facility replacement
The city awarded the design-build contract for its third water plant, the first to use reverse osmosis, which officials say will deliver exceptional water quality. A groundbreaking is being planned with public education on water quality.