Abandoned vehicles and pothole hazard on flooded roads
Weeks of rain saturated the ground, and traffic over softened roads is creating potholes citywide — some hidden underwater. Crews are making temporary and long-term repairs, and more potholes are expected as the ground dries.
Mackey Marshall road and Southern Grove infrastructure complete
The city is fronting up to $20.3 million so Mattamy Homes can finish the missing north-south link between Crosstown Parkway and Discovery by the end of 2027 — something the original development schedule didn't require until 11 years later. It means faster routes, better fire/EMS response, and enables the planned western fire station and school site.