Village Green Drive funding gap
Summary
The CRA missed out on the federal BUILD grant for widening Village Green Drive despite planning to pledge $12.5 million in TIF revenue as a match. Staff will make the project shovel-ready by year's end and pursue phased construction and other funding sources.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
About $12.5 million in pledged CRA matching funds now stays in reserve pending a new funding strategy.
Commuters in the Village Green corridor would eventually gain a widened four-lane road once funding is found.
Residents near Village Green Drive wait longer for congestion relief after the grant loss.
Mentions & discussions (3)
Community Redevelopment Agency — September 28, 2026
The CRA missed out on the federal BUILD grant for widening Village Green Drive despite planning to pledge $12.5 million in TIF revenue as a match. Staff will make the project shovel-ready by year's end and pursue phased construction and other funding sources.
City Council Workshop — July 22, 2026
The city didn't get the federal construction grant. The CRA may fund a $12.5 million phase, with phasing options and other grant and appropriation strategies being pursued before the March 2028 soccer stadium opening.
City Council Workshop — February 19, 2026
The 60% design is in for the $2 million RAISE-grant corridor project, with a $24 million path to construction money. Council leaned toward the peanut roundabout and reverse-angle parking — and wants a bigger plan for zoning and redevelopment before private sales reshape the corridor.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Port St. Lucie
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.