MediumWater Utilities

$1 Surcharge on Paper Utility Bills

Mailing paper water bills to about 18,000 households costs roughly $220,000 a year — and it's growing. The council backed a $1 monthly surcharge on paper bills, which Vice Mayor Grubbs framed as a small, Amendment-3-era efficiency win. A formal vote comes later.

1 mention (1 this month)Last discussed Nov 17, 2026
HighWater Utilities

Regional biosolids facility with Volusia County

The city is buying about $3 million worth of land near Dunlawton and Spruce Creek for an roughly $80 million sewer plant rehab, avoiding about $4 million for a temporary facility instead.

2 mentionsLast discussed Sep 1, 2026
MediumWater Utilities

Public Utilities Field Operations Facility Completion

1 mentionLast discussed Aug 4, 2026
HighWater Utilities

Utility Rate Increase — Final Year of Four-Year Plan

Water, sewer and reclaimed fees go up one last time under the 2023 Rate Study, about $10 a month for a typical household. Residents on fixed incomes pushed back hard, but the council said the enterprise fund must cover costs and rates remain among the lowest in Volusia County.

5 mentionsLast discussed Jun 16, 2026
HighWater Utilities

Cambridge Canal Pump Station wetland mitigation credits

The first major flood-control project is going to construction this spring, finishing around spring 2027. It targets the city's second-largest flooding area.

2 mentionsLast discussed Mar 17, 2026
HighWater Utilities

Master meter ordinance for private water systems

The city wants to stop reading water meters inside five parks on private land — a practice with no legal agreements behind it. Residents worry park owners will pass infrastructure costs on to tenants, especially seniors on fixed incomes.

5 mentionsLast discussed Feb 17, 2026
HighWater Utilities

Water, Wastewater and Utility Fee Increases

The council adopted new utility fees on consent, part of a phased increase stemming from a 2022 rate study. Residents pushed back, saying bills are already high and questioning future costs tied to water treatment.

1 mentionLast discussed Jan 13, 2026