Stormwater and Flood Mitigation Projects
Summary
Two of three property owners have rejected the city's purchase offers for the pond project that would help the flooded FPL substation area. The city won't overpay, so the project may fall apart entirely.
At a glance
- Total mentions
- 11
- Last 30 days
- 3
Rising — discussed at 3 meetings since Oct 20, 2026, up from 1 in the two months before.
Impact analysis
Federal Transform 386 dollars could be lost if the property deals collapse.
If it proceeds, the neighborhoods around the FPL substation that flood repeatedly.
Property owners declined their offers; neighbors keep flood risk if the project dies.
Mentions & discussions (12)
City Council - Nov 17, 2026
Two of three property owners have rejected the city's purchase offers for the pond project that would help the flooded FPL substation area. The city won't overpay, so the project may fall apart entirely.
City Council - Nov 4, 2026
The Cambridge Pump Station — protecting roughly a third of the properties that flooded in recent storms — starts construction in early 2027. A new FEMA grant cycle opened for homeowners whose homes flooded, and the city may resubmit Sugar Forest and wastewater plant projects for Transform386 funding to lower its $8 million match.
City Council - Oct 20, 2026
The Cambridge Pump Station — the first major stormwater master plan project — goes out to bid for construction by January, aiming to be ready before the 2028 hurricane season. The city has about $40 million of a roughly $60 million stormwater program funded and is chasing Transform386 grants to close the gap.
City Council - Aug 19, 2026
A regional report showed Port Orange has secured over $22 million in Transform 386 flood grants, with drainage work underway in Sugar Forest, Sleepy Hollow, Portona, and Powers Avenue, plus canal watershed studies. A new county dashboard lets residents look up flood projects near their address.
City Council - Jul 21, 2026
The city's $60 million stormwater program has $40 million in outside funding secured, three acquired properties have been cleared, Transform 386 projects start construction in fall 2026, and a new federal BRIC grant window just opened. The Sugar Forest project is at 75% design.
City Council - May 19, 2026
Demolition of three flood-prone homes the city bought starts in July; Cambridge project bids are due May 29 with construction possibly starting late summer. The county is also building a regional stormwater tracking dashboard cities can feed into.
City Council - May 5, 2026
Cambridge pump station bids are due May 15, and FEMA-funded agreements coming in June will elevate 13 homes east of Nova Road, with construction expected in early 2027.
City Council - Apr 7, 2026
Jackson/Oak is nearly done, Cambridge pump station bids are due May 1 with construction starting this summer, Sugar Forest is at 60% design, and the Portona and Powers Avenue projects are entering design. Thirteen homes are slated for flood elevation funding by 2027.
City Council - Mar 3, 2026
The city is buying 846 Bears Trail for the Nixon Lane stormwater pond and pump station, and officials continue working flood relief for Nova Canal and Cambridge-area neighborhoods, with a federal study pointing to large pumps as the long-term fix.
City Council - Feb 17, 2026
The city is buying repeatedly flooded homes, demolishing them, and using the land for green space, canals access, or stormwater ponds and pumps. Two purchases were 75% reimbursed by a federal/state grant, and the Bears Trail parcel anchors a pond and pump station that will push water straight to the Halifax River. Officials stressed every project helps the whole city because water doesn't stop at property lines.
City Council - Feb 3, 2026
Two smaller drainage projects came out of resident field visits after the hurricanes — a pond on Devon Street that overflows into neighbors' yards and a Sweetwater Boulevard system that spills over when full.
Port Orange to tear down 3 homes to mitigate future flooding
Port Orange to tear down 3 homes to mitigate future flooding Spectrum News 13
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Port Orange
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.