Charles Street Road Conditions

Summary

Resident Robert Fleck called Charles Street the worst road in the city — a 'washboard' for cyclists — and brought photos. Staff explained resurfacing now would be wasted because a major stormwater project with an 8,000-foot, 36-inch pipe will tear the street up; the east side gets work in August.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 21, 2026.

Impact analysis

✅Who benefits

Charles Street residents and cyclists once the coordinated stormwater and repaving project is complete.

⚠️Who could be affected

Residents living with the deteriorated road in the interim.