Flood insurance rating protection
Adopting the county's updated mitigation strategy keeps the city compliant with flood insurance rating requirements — which helps keep residents' flood insurance premiums lower.
$2.5 Million Sewer System Rehabilitation Funding
The council redirected $2.5 million from two existing capital projects to fix defects in the city's sanitary sewer system. The repairs are required to bring the city into compliance with Miami-Dade County code — an environmental and public-health issue for neighborhoods served by those lines.
8.5% Water and Sewer Rate Increase
Your water bill goes up 8.5% starting October — wholesale water and wastewater costs jumped $3.25 million. The city has no money to build its own water plant; the $350 million Wifia loan hasn't even been applied for yet.
Winson Water Treatment Plant reliability improvements
Council approved Amendment No. 1 to the state revolving fund loan for the Winson Water Treatment Plant upgrades — the paperwork that keeps the water plant reliability project moving.
Utility billing switch to monthly
Water and sewer bills will now come monthly instead of quarterly starting around January. Supporters say smaller bills are easier to manage and catch up on; critics worry about fixed-income residents who already struggle to pay.
Smart water meters (AMI) and utility collections
The city is collecting only about half of what it bills, with $38.2 million in receivables. The council debated monthly billing, enforcement of shutoffs, and accuracy of commercial meters.
Sewer Improvements at Breezeswept Park and Tot-Lot
A $109,197.87 impact fee refund from developer Bellamonte at Golden Glades will go toward sanitary sewer improvements at Breezeswept Park and Tot-Lot — facilities residents have been actively requesting. This improves park amenities and sanitation infrastructure in the area.
2025 Stormwater Master Plan adoption
The plan identifies 22 flood-prone spots needing about $11 million in short-term drainage fixes over five years, plus long-term projects. A resident challenged the accuracy of Third Court mapping before the 4-1 adoption.
Water service area transfer with North Miami Beach
North Miami will take over water service for the Joe Celestin corridor parcels, letting the Redwood development connect to city infrastructure instead of North Miami Beach's.
Arch Creek pipeline replacement
The city ratified a $1.46 million emergency contract to replace a 10-inch asbestos cement water pipe along NE 135th Street — critical water infrastructure work.