Cagni Park North Phase I cost overrun
Summary
The park project was bid about $500K over its $17.5 million funding before design costs, and now needs another $1 million in contingency. HVAC delays push the aquatics building work to July; final completion is targeted for September 9, 2026.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 10, 2026.
Impact analysis
Up to $1 million more on top of prior contingency draws, coming from general funds and pension savings.
Residents who will use the new pool, fields, playground and parking at Cagni Park North.
Taxpayers absorb the growing cost of a project that started over budget.