Redwood Mixed-Use Development — CUP Amendment One (PC 17-124)
Description
The Redwood developer asked to swap the planned Claude Pepper Park pool for soccer fields (keeping the splash pad) and to build the 27.67-acre project in three phases for financing reasons. The commission recommended approval 6-0 with pool-related recommendations.
Impact summary
Construction could start on the first two buildings around September or October; the park improvements are also in the first phase, pending county environmental review.
Applicant
- Name
- Redwood CUP Developers LLC
- Address
- 1255 NW 135th Street and 1525 NW 135th Street
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 2
Last vote · Planning Commission
A recommendation. The council’s outcome is not on record here.
Last discussed Jun 25, 2026.
Meeting timeline (2)
Planning Commission - Jun 25, 2026
The Redwood developer asked to swap the planned Claude Pepper Park pool for soccer fields (keeping the splash pad) and to build the 27.67-acre project in three phases for financing reasons. The commission recommended approval 6-0 with pool-related recommendations.
Regular Council — March 10, 2026
The developer is ready to build as originally contemplated, or to remove the pool and give the city a $3 million credit. Any change requires a CUP amendment.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.