7 issues in water utilities with high priority
Clearwell tank rehabilitation
The city wants to spend about $426,000 — plus bond fees and a $15,000 contingency — to rehabilitate one of its two water clearwell tanks. This keeps the water treatment plant running reliably.
Utopi water meter rate adjustment deferred to December
A proposed ordinance would revise water and sewer rates and set up a five-year rate plan based on a study by GovRates Inc. Staff is asking to defer the vote to December 8, so residents will have more time to weigh in.
Privatizing utility billing and customer service
The city is picking a contractor to run meter reading, billing, collections, and customer service — functions that affect how residents get and question their water bills. Inframark, Inc. was ranked highest by the evaluation committee.
Drainage Flooding in Broadview and Patron Village
Commissioners described residents with water in their homes, ruined carpets, and blocked drains in Broadview and areas near 50th Avenue. They called for a citywide flood assessment and site visits to the hardest-hit areas.
Water treatment plant operations contract
The city is choosing a firm to manage and operate its water treatment plant — the operation that keeps tap water safe and flowing. Inframark, Inc. topped the evaluation committee's rankings.
Stormwater assessment rising from $140 to $200
Stormwater fees would go up $75 to $200 per ERU to fund drainage projects — but even with the increase, the fund still needs about $1 million from reserves to cover planned expenses.
FY2027 Water Management System Assessment Rate
The district board was scheduled to set a preliminary $200-per-unit assessment for the water management system, which funds drainage and flood control across the district. A public hearing would follow before the rate is final.