CR 121 Road Reconstruction and Detour Impacts
Summary
Heavy trucks cutting through Horseshoe Circle during the CR 121 road construction project have created concerns for local residents. The board approved temporary 'No Thru Trucks' and 'Local Deliveries Only' signs to keep commercial truck traffic off neighborhood roads.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Mar 23, 2026.
Impact analysis
Minimal cost for signage installation by county staff.
Residents living along Horseshoe Circle and adjacent residential roadways affected by construction detours.
Taxpayers funding the higher project cost and residents experiencing extended construction durations.
Mentions & discussions (2)
Nassau County Board of County Commissioners - Mar 23, 2026
Residents raised major concerns about emergency response times, school bus routes, and therapy disruptions caused by full road closures on County Road 121. The board approved a $2.38 million change order to provide a one-lane open alternative during construction.
Nassau County Board of County Commissioners - Jan 21, 2026
Heavy trucks cutting through Horseshoe Circle during the CR 121 road construction project have created concerns for local residents. The board approved temporary 'No Thru Trucks' and 'Local Deliveries Only' signs to keep commercial truck traffic off neighborhood roads.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Nassau County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.