Cortez Bridge Construction Staging on County Property
Summary
The county will let the Cortez bridge contractor use county land — including a parcel residents say was promised as overflow parking only — in exchange for the contractor waiving roughly $1.4 million in delay claims. Neighbors feel blindsided; business owners warned the alternative would bring daily lane closures past their restaurants.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 20, 2026.
Impact analysis
Waiver of roughly $1.4 million in potential construction delay claims against the county.
Beach-goers and commuters who avoid lane closures, and the county's exposure to delay claims.
Cortez north-side residents concerned about construction traffic through their sole access intersection.
Mentions & discussions (2)
Board of County Commissioners (Regular) — October 20, 2026
The county will let the Cortez bridge contractor use county land — including a parcel residents say was promised as overflow parking only — in exchange for the contractor waiving roughly $1.4 million in delay claims. Neighbors feel blindsided; business owners warned the alternative would bring daily lane closures past their restaurants.
Board of County Commissioners (Regular) — June 16, 2026
FDOT's contractor wants to use the county's $13 million seafood shack property as staging for four years for about $300,000 in work; the board approved negotiations plus a 60-day right of entry limited to south-side parcels after concerns about residents and lost park plans.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Manatee County
What the council decided, in plain English — one email a week.