Tennessee Avenue sidewalk change order
Summary not yet generated for this topic.
Community sentiment
Concerned (1)Neutral (1)
At a glance
- Public comments
- 2
- Last 30 days
- 2
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Public comments (2)
NeutralUnidentified Resident (Mr. Oakley)Oct 13, 2026
Asked what the change order covered; learned it was about $8,500 in drainage work, 100% grant-funded.
City Commission - Oct 13, 2026 · 11:00 →ConcernedBarbara DayOct 13, 2026
Questioned the $623,000 contract total and asked whether ADA compliance issues explained a ~$90,000 item; the city manager corrected her.
City Commission - Oct 13, 2026 · 11:54 →