Woodside Drainage Phase 2 Inspection
Summary
A $931,691 inspection services contract moves the Woodside neighborhood drainage and utility improvements forward.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
$931,691.34 for construction engineering inspection services.
Woodside-area residents facing drainage and flooding problems.
Developers might face stricter building rules and higher costs, which could slow down certain local projects.
Mentions & discussions (5)
City Commission - Jun 2, 2026
Easement agreements were approved so the Woodside Drainage & Utility Phase 2 project can move forward, improving stormwater and utility infrastructure.
Kissimmee seeks public input on flood risk plan
Kissimmee seeks public input on flood risk plan WFTV
City Commission - Mar 17, 2026
An amendment to the state flood-mitigation grant agreement keeps the Woodside drainage project on track.
City Commission - Feb 17, 2026
A $9.76 million contract moves Phase 2 of drainage and utility work forward, aimed at flooding and infrastructure improvements.
City Commission - Feb 3, 2026
A $931,691 inspection services contract moves the Woodside neighborhood drainage and utility improvements forward.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Kissimmee
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.