Passive Park Buffer Replacement
Summary
The passive park will be built by the same contractors right after the trail segment, starting around late June. Permits are cleared; bollard and lighting choices are the last detail. Landscaping will be native and low-maintenance.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Aug 24, 2026.
Impact analysis
Homeowners won't pay — the Jacksonville Tree Board is covering every tree and plant, over 100 in all.
Southend residents gain an activated, connected park space.
Mentions & discussions (2)
Community Redevelopment Agency - Aug 24, 2026
Clearing at the passive park revealed the buffer behind 14 homes is mostly invasive and dead plants. The Jacksonville Tree Board is footing the bill for 100+ new trees and shrubs, and staff will door-hang residents before more clearing. Project stays on track for late September/early October.
Community Redevelopment Agency - May 18, 2026
The passive park will be built by the same contractors right after the trail segment, starting around late June. Permits are cleared; bollard and lighting choices are the last detail. Landscaping will be native and low-maintenance.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Jacksonville Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.