10th Street South Infrastructure Improvements – Phase II Contingency
Summary
The city is finishing the complete rebuild of 10th Street South from 5th Avenue to Beach Boulevard — new water, sewer, and stormwater lines plus roads and sidewalks. Expect detours and construction disruption for about 14 months, with extra care planned around the school in the corridor.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 21, 2026.
Impact analysis
$6.59 million for construction, plus $140,739 for contract administration and $128,000 for inspection — about 15% under the engineer's $7.47 million estimate.
Residents and businesses along the 10th Street South corridor get modern utilities, better roads, and improved drainage.
Drivers and nearby residents will face detours and construction noise for the duration of the roughly 14-month project.
Mentions & discussions (2)
City Council - Sep 21, 2026
The big 10th Street South road project ate through most of its original $600,000 contingency, so the council added another $300,000 to keep construction moving. Expect that project to keep costing more than first bid.
City Council - Feb 17, 2026
The city is finishing the complete rebuild of 10th Street South from 5th Avenue to Beach Boulevard — new water, sewer, and stormwater lines plus roads and sidewalks. Expect detours and construction disruption for about 14 months, with extra care planned around the school in the corridor.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Jacksonville Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.