Wabasso community transportation concerns
Summary
Residents say Wabasso has been left out of transportation planning: dangerous sidewalks, only one route out of the community across US 1 and the railroad tracks, and no meaningful engagement. The board agreed to a future agenda item reviewing what's been done and planned for the area.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 10, 2026.
Impact analysis
The CR 510 widening project is already a funded priority, but near-term safety fixes remain unclear.
Wabasso and north county residents if the promised review leads to action.
Wabasso residents, particularly schoolchildren crossing 510/512 and anyone needing emergency access east of the tracks.
Mentions & discussions (2)
Metropolitan Planning Organization (MPO) - Jun 10, 2026
FDOT laid out the status of all six segments of the CR 510 widening, with construction ahead of schedule on the first segment and Segments 5 and 6 delayed by water management district permits. Wabasso residents sharply criticized the $105 million flyover, saying the money should serve their historically Black community's safety and hospital access instead. FDOT defended the design as driven by FEC Railroad requirements and extensive outreach.
Metropolitan Planning Organization (MPO) - Apr 8, 2026
Residents say Wabasso has been left out of transportation planning: dangerous sidewalks, only one route out of the community across US 1 and the railroad tracks, and no meaningful engagement. The board agreed to a future agenda item reviewing what's been done and planned for the area.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Indian River County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.