Unified Planning Work Program FY 2026/27–2027/28
Summary
The UPWP sets the MPO's planning agenda and roughly $1.6 million budget for July 2026 through June 2028, funded mainly by federal grants. It's smaller than the last cycle because the pricey 2050 long-range plan is done, and unused funds roll into a reserve for the next long-range plan.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Apr 7, 2026.
Impact analysis
About $1.6 million over two years, nearly all federal grant money — no direct hit on local taxpayers.
Anyone who benefits from transportation planning — trail users, transit riders, and drivers alike.
Mentions & discussions (3)
MPO Citizen Advisory Committee - Apr 7, 2026
The UPWP sets the MPO's planning agenda and roughly $1.6 million budget for July 2026 through June 2028, funded mainly by federal grants. It's smaller than the last cycle because the pricey 2050 long-range plan is done, and unused funds roll into a reserve for the next long-range plan.
MPO Technical Advisory Committee - Mar 27, 2026
The UPWP is the MPO's work and budget plan for July 2026 through June 2028 — funding traffic counts, planning studies, transit planning, and public outreach at just over $800,000 a year. It sets up a greenways plan update and regional planning work with Martin and St. Lucie counties.
MPO Technical Advisory Committee - Jan 23, 2026
Staff previewed big planning projects for the next two years, including the county's first Greenways Plan update in over 15 years and a possible bicycle/pedestrian master plan refresh, plus regional long-range planning with the other Treasure Coast MPOs. Adoption comes in April.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Indian River County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.