Offshore sand supply for future beach projects
Summary
The county currently depends on a mine in St. Lucie County, its only approved offshore borrow site sits at the far southern county line, and nearshore reefs block dredging in Sectors 4 and 5. Members urged early planning so a hurricane doesn't force a scramble.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
Truck haul costs more per cubic yard, but dredge mobilization fees run around $5.1 million, making source decisions a major budget driver.
Taxpayers benefit if cheaper, closer sand sources are secured before the next project or storm.
Mentions & discussions (2)
Beach & Shore Preservation Advisory Committee - Jun 15, 2026
Staff say the county's ready supply is the South Borrow Site's 2.5 million cubic yards of permitted sand. A massive federal-water resource (682 million cubic yards) exists offshore, but federal permitting could take 5–10 years, so staff recommend waiting and monitoring.
Beach & Shore Preservation Advisory Committee - Apr 20, 2026
The county currently depends on a mine in St. Lucie County, its only approved offshore borrow site sits at the far southern county line, and nearshore reefs block dredging in Sectors 4 and 5. Members urged early planning so a hurricane doesn't force a scramble.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Indian River County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.