Integrated Water Master Plan progress
Summary
The county's 20-year water and sewer blueprint is about 75% done, with demand forecasts, treatment options, and hydraulic modeling underway. A second round of public input comes in late spring or early summer.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Sep 15, 2026.
Impact analysis
About $470,000 of the approved $742,000 contingency remains; the 20-year build-out will drive future utility rates and capacity.
Everyone on county water and sewer, as the plan shapes capacity for growth over the next two decades.
Mentions & discussions (3)
Board of County Commissioners - Sep 15, 2026
The county's 20-year water and sewer master plan slipped to February or March after a key consultant turnover and hydraulic modeling delays. The plan is meant to be a living, digital document with a 20-year capital improvement plan.
Board of County Commissioners - Jun 2, 2026
The county's 20-year roadmap for water, wastewater, and reuse systems is now expected to finish in fall 2026 — a few months later than planned, mainly because calibrating the hydraulic model took longer than expected. About $470,000 of the approved contingency remains.
Board of County Commissioners - Mar 10, 2026
The county's 20-year water and sewer blueprint is about 75% done, with demand forecasts, treatment options, and hydraulic modeling underway. A second round of public input comes in late spring or early summer.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Indian River County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.