104th Avenue status
Summary
Good news: Public Works will cape-seal (chip-seal) 104th Avenue's north and south sections out of its own operating budget — roughly $350,000 — at no cost to the MSTU fund, though no date was given.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 22, 2026.
Impact analysis
About $350,000, paid by Public Works' operating budget rather than the MSTU fund.
Residents of and travelers on 104th Avenue, who get a resurfaced road without MSTU cost.
Residents endured months of extra delay on a badly deteriorated road.
Mentions & discussions (2)
Vero Lake Estates Municipal Service Taxing Unit Advisory Committee - Oct 22, 2026
The long-awaited 104th Avenue resurfacing was supposed to start in August, but rains and Hurricane Isaias pushed it to early December. The county will fund the Cape Seal work itself — not from MSTU funds — and approved weekend work to speed things up.
Vero Lake Estates Municipal Service Taxing Unit Advisory Committee - Jul 23, 2026
Good news: Public Works will cape-seal (chip-seal) 104th Avenue's north and south sections out of its own operating budget — roughly $350,000 — at no cost to the MSTU fund, though no date was given.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Indian River County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.