A1A flooding, drainage maintenance and resiliency partnership with FDOT
Summary
Sunny-day and king-tide flooding on A1A dominated the meeting. FDOT's drainage engineer explained twice-a-year backflow preventer inspections, but board members said the pipe system itself is only inspected reactively — and they want a scheduled, proactive inspection protocol. Two additional pump stations (Jefferson and Foxclove, ~$22.5M) still need funding partners.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 6, 2026.
Impact analysis
The new backflow preventers cost up to $1.32 million; two more pump stations would cost roughly $22.5 million and the CRA has already spent $450,000 on design.
Beach residents, tourists, and businesses along A1A who deal with tidal street flooding.
Beach residents continue to suffer flooded streets until the full pump and inspection program is completed.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hollywood