Medium PriorityParks Recopen

Liza Jackson Park Improvements

Summary

A $3.14 million contract will deliver new restrooms, revamped boat trailer parking, stormwater and vehicle parking at the waterfront park, with work starting August 1 to avoid disrupting summer boat ramp use. Costs grew from a $2 million estimate to about $3.5 million with design.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Mar 24, 2026.

Impact analysis

💰Financial impact

$3,139,269.93 from CRA restricted fund balance, offset by a $1 million county commitment and possible Landing reimbursements.

✅Who benefits

Boaters, parkgoers and west-side residents get upgraded restrooms, parking and stormwater facilities.