King's Landing Development — Fourth Amendment to Development Agreement
Description
The developer missed a milestone for submitting hotel vertical plans; a fourth amendment with corrected milestone dates will come back for approval around May 12, 2026, keeping the July 11, 2028 hotel completion date.
Impact summary
This waterfront redevelopment's fate — and the city's protections under the agreement — will be shaped by the FPRA's direction.
Applicant
- Name
- Live Oak Holdings / Audubon Development
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 2
Recorded in the meeting
Last discussed Jul 13, 2026.
Meeting timeline (2)
City Commission Day Meeting & Budget Workshop — July 13, 2026
The developer's proposed amendments to the Kings Landing development agreement drew sharp pushback, with commissioners citing a possible material breach and risks to the reverter clause. A presentation goes to the FPRA board before anything returns to the commission.
FPRA Regular Meeting (Business) — April 14, 2026
The developer missed a milestone for submitting hotel vertical plans; a fourth amendment with corrected milestone dates will come back for approval around May 12, 2026, keeping the July 11, 2028 hotel completion date.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Fort Pierce
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.