Quarterly update on the King's Landing project: civil plans are complete and go to the city for review by January 16, 2026; the Marriott hotel agreement is progressing; Keller Williams will market the residential condos.
Impact summary
Phase 1 is tracking toward delivery by July 2028, bringing new hotel, condo and retail development downtown.
Applicant
- Name
- Live Oak Holdings
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 4
Last vote · City Commission
Last discussed Sep 14, 2026.
Meeting timeline (4)
City Commission Special Meeting - Kings Landing (Special) — September 14, 2026
Live Oak requested and received a six-month extension to secure $15 million in hotel equity, conditioned on a Fourth Amendment being finalized within 30 days; the developer is technically in default of the Third Amendment.
FPRA Regular Meeting (Business) — July 14, 2026
The developer reported permitting progress but is in default on milestone deadlines, and pitched the city for $15 million in bond financing for 60% ownership of the hotel after Main Sail's investors balked. The board took no vote and asked for a financing timeline within two weeks.
FPRA Regular Meeting (Business) — April 14, 2026
Quarterly update from developer Bill Ware, who requested a fourth amendment to the milestone timeline aimed at protecting the July 11, 2028 hotel completion date.
FPRA Regular Meeting (Business) — January 14, 2026
Quarterly update on the downtown King's Landing project — civil plans are complete and being submitted for city review, and the Marriott hotel franchise approval is expected next month.
Related issues (3)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Fort Pierce
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.