Central Wastewater Treatment Facility Surface Water Discharge Elimination

Summary

Council approved a $137.6 million progressive design build project to eliminate surface water discharge to the Caloosahatchee River.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 15, 2026.

Impact analysis

💰Financial impact

Total project cost of $137,656,641.29, with $52.5 million secured and an anticipated $85 million bond issuance.

✅Who benefits

Fort Myers utility ratepayers and regional water quality.