Six-unit cluster development / flooding
Summary not yet generated for this topic.
Community sentiment
At a glance
- Public comments
- 4
- Last 30 days
- 4
Discussed at 1 meeting in the last 60 days; most recently Oct 22, 2026.
Public comments (4)
A 30-year resident of 14th Court says the street now floods repeatedly — twice in six weeks — and blames the nearby eight-unit project built up on four feet of fill. She urged the board not to make it worse with six more units.
Planning and Zoning Board - Oct 22, 2026 · 52:33 →The River Oak Civic Association president, a 60-year neighborhood resident, guaranteed the project will make flooding worse, mocked the trash plan (18 containers along the street), and said developers' drainage promises never hold.
Planning and Zoning Board - Oct 22, 2026 · 1:09:54 →Lives one block away on 15th Street where groundwater bubbles up in yards; asked the developer to use pervious materials for patios and driveways because the ground there is already saturated.
Planning and Zoning Board - Oct 22, 2026 · 1:24:08 →Told a cautionary tale: townhouses built next to his 40-year-old duplex raised the grade and created 'Lake McNamara' in his front yard after normal rain. He blamed the buildings, not the city.
Planning and Zoning Board - Oct 22, 2026 · 1:25:29 →