Wastewater Treatment Plant capital projects
Summary
The city refinanced its state wastewater loans at favorable rates — the finished projects close out at 0% interest and the remaining electrical project gets $17.5 million at 2.16%, far below the ~4.8% market rate.
At a glance
- Total mentions
- 9
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Nov 5, 2026.
Impact analysis
Saves ratepayers money by locking in a 2.16% rate versus the 4.78% market rate on $17.5 million.
Water and sewer customers, who avoid higher debt costs on the utility system.
Mentions & discussions (9)
CITY COMMISSION (Regular) - Nov 5, 2026
The city refinanced its state wastewater loans at favorable rates — the finished projects close out at 0% interest and the remaining electrical project gets $17.5 million at 2.16%, far below the ~4.8% market rate.
CITY COMMISSION (Regular) - Oct 22, 2026
Resolution 26-23 would let the city pay for water and wastewater projects now and reimburse itself later with up to $8 million in tax-exempt bonds or notes. It's a financing step that shapes how big utility improvements get paid for.
CITY COMMISSION (Regular) - Sep 3, 2026
The city quietly ratified a nearly $96,000 emergency buy of two new 4,600-gallon bleach tanks at the wastewater treatment plant after the old ones failed.
COMMISSION WORKSHOP - Sep 1, 2026
The state funded $1.5 million to replace the last remaining unlined water pipe in the city system, buried under brick streets along Alt. U.S. 19 — a project that's been pursued since the 1990s.
CITY COMMISSION (Regular) - Jul 23, 2026
Two contracts totaling about $3 million were awarded to keep the wastewater plant reliable: obsolete pump replacement and emergency generator building hardening ahead of hurricane season.
CITY COMMISSION (Regular) - Jun 4, 2026
The wastewater treatment plant filter and basin rehab bid came in about $1.45 million over budget, requiring the big chunk of the budget amendment.
CITY COMMISSION (Regular) - May 21, 2026
Five of the city's 47 lift stations are getting a $922,000 overhaul to fix aging sewer infrastructure and keep groundwater and rainwater from overwhelming the system.
CITY COMMISSION (Regular) - Feb 5, 2026
An $85,445 pump purchase was on the agenda to help keep sewage moving during power outages and avoid overflows at the city's 43 lift stations.
CITY COMMISSION (Regular) - Jan 8, 2026
The city is fixing 24 aging sewer manholes for $79,880, prioritizing coastal spots vulnerable to storm-surge infiltration, plus refurbishing two aging wastewater treatment bar screens for $144,079.71.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dunedin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.