Summary

The city is spending $326,672 to drill its 30th well — built for hurricane resilience after storm surge knocked out wells, not for growth. Above-ground work will cost another $300,000–$400,000.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Sep 3, 2026.

Impact analysis

💰Financial impact

$326,672 now, plus $300,000–$400,000 for piping, electrical, and controls later.

✅Who benefits

All water customers, who gain a more storm-resilient well field.