Marina Repair and Master Plan Progress

Summary

The east bulkhead should be substantially complete by late November, but paving slips to just before Christmas and the fishing pier is still stuck waiting on a federal fisheries permit review. Staff are documenting contractor delay damages and planning alternative boat parade viewing.

At a glance

Total mentions
6
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Nov 5, 2026.

Impact analysis

💰Financial impact

The city is calculating delay damages including lost boat ramp and slip revenue and extra consultant costs for possible recovery from the contractor.

✅Who benefits

Boaters and marina users once the seawall, docks, and pier are restored.

⚠️Who could be affected

Residents awaiting the reopened fishing pier and boat ramp, and marina businesses affected by the prolonged construction.

Mentions & discussions (6)

MeetingNov 5, 2026

CITY COMMISSION (Regular) - Nov 5, 2026

The east bulkhead should be substantially complete by late November, but paving slips to just before Christmas and the fishing pier is still stuck waiting on a federal fisheries permit review. Staff are documenting contractor delay damages and planning alternative boat parade viewing.

MeetingSep 3, 2026approved

CITY COMMISSION (Regular) - Sep 3, 2026

Slip fees go up 7% on October 1 instead of the planned 10%, helped by a $3 million state grant. But if FEMA doesn't fully fund the replacement of hurricane-damaged Docks A and B with floating docks, more increases could follow.

MeetingJun 4, 2026

CITY COMMISSION (Regular) - Jun 4, 2026

The hurricane-damaged bulkhead repair contractor is months behind, pushing completion to late August/September. The fishing pier still waits on an Army Corps permit, and dock design work continues.

MeetingMar 19, 2026approved

CITY COMMISSION (Regular) - Mar 19, 2026

Kimley-Horn & Associates was hired for $355,757 to design and permit the replacement of marina Docks A and B, a key piece of the marina recovery.

MeetingMar 3, 2026

COMMISSION WORKSHOP - Mar 3, 2026

Hurricane-damaged docks, the boat ramp, and the harbormaster building are slated for phased replacement, with floating docks preferred and FEMA reimbursement expected for much of the cost. Commissioners want the timeline accelerated — dock replacement isn't projected until FY 2028-2029 — and slip rate increases of 7-10 percent a year are baked into the fund forecast.

MeetingJan 8, 2026approved

CITY COMMISSION (Regular) - Jan 8, 2026

The hurricane-destroyed fishing pier finally has a contractor. Demo starts as early as March, with the city aiming for completion before the December 1 boat parade; the ferry and marina operations should continue.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Dunedin

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.