Gladys Douglas Preserve Phase II Development
Summary
Designs for pavilions, restrooms, a pier and kayak launch are at 90%, but costs exceed the roughly $2.3 million budget. The project will go to bid with add-alternates so the city can buy what it can afford.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
Costs exceed the $650,000 design and $1,650,000 construction budget; add-alternates will be bid separately.
Dunedin residents and the whole county gain access to the last rosemary scrub in Pinellas County and Jerry Lake recreation.
Fans of the pier and pavilion amenities may wait longer if bid prices don't come in favorable.
Mentions & discussions (1)
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dunedin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.