FY 2026 Street Resurfacing Program
Summary
About 30 streets get milled and repaved this year under a $1.53 million contract, with the low bid allowing extra curbing and the addition of Robmar Drive. Expect construction disruption in late April through July.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 4, 2026.
Impact analysis
$1,529,649.58 total, paid from Penny, Stormwater, and Gas Tax funds — not general property tax.
Residents on the 30 repaved streets, plus drivers citywide.
Potentially, brick street homeowners if a special assessment is later adopted.
Mentions & discussions (3)
BUDGET WORKSHOP - Aug 4, 2026
Gas tax revenue keeps shrinking as cars go electric, so staff proposes shifting $125,000 of sidewalk maintenance to the Risk Fund starting FY28 — and adding it to legislative priorities.
COMMISSION WORKSHOP - Jul 7, 2026
Brick streets have been underfunded in Penny IV, and a $5 million request is in for Penny V. Commissioner Sandbergen floated asking homeowners on brick streets for an assessment; Mayor Freaney noted brick streets have historically been a break-even versus paved roads. Staff would study assessment options if directed.
CITY COMMISSION (Regular) - Mar 19, 2026
About 30 streets get milled and repaved this year under a $1.53 million contract, with the low bid allowing extra curbing and the addition of Robmar Drive. Expect construction disruption in late April through July.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dunedin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.