Splash pad improvements contract award
Summary
The city's splash pad project would move forward if the council awards the contract to SP One Repairs, LLC for $154,900, with a 6% contingency bringing the total to $164,194.
At a glance
- Total mentions
- 3
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 18, 2026.
Impact analysis
Total contract cost of $164,194 including contingency.
Families and kids who use the city's splash pad recreation facility.
Mentions & discussions (3)
Special City Council Meeting — 2026-11-18
The city's splash pad project would move forward if the council awards the contract to SP One Repairs, LLC for $154,900, with a 6% contingency bringing the total to $164,194.
Special City Council Meeting — 2026-08-19
The splash pad fixtures are custom-made with a 20-week lead time, so the city is paying its deposit now to hit the November–March construction window. The ECHO grant covering the project has cleared every review so far.
Special City Council Meeting — 2026-06-17
The 14-year-old splash pad at 137 S. Highway 17-92 gets a full overhaul — new fixtures, refinished pad, new pump system — funded through a $250,000 ECHO grant plus $6,000 for signage, built next off-season with a spring 2027 reopening.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for DeBary
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.