Benson Junction Road Reconstruction cost growth and phasing
Summary
The Benson Junction road project has more than doubled to over $10 million since its original $5.7 million design. The city is splitting it into two phases — utilities and flood fixes first, road construction later — and will chase more grant money this November.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 5, 2026.
Impact analysis
$158,886 now for phase-one engineering, funded from reserves, plus millions more to be sought from grants.
Residents and businesses in the chronically flood-prone Benson Junction area, plus commuters who use the road.